Terminus Centre-ville - Construction of three elevators

The provision of three elevators in the building housing the Terminus Centre-ville will enable people with reduced mobility to move around independently between the terminal, Bonaventure metro station and De la Gauchetière Street.

This major project will cause temporary disruption inside the terminal. In addition, platform 20 will be closed for the duration of the work, resulting in platform changes for certain Réseau de transport de Longueuil lines.

The Réseau de transport métropolitain (RTM) undertakes to limit any inconvenience to customers by carrying out most of the work outside peak hours.

This $9.3-million investment is 75% funded by the Ministère des Transports, de la Mobilité durable et de l’Électrification des transports (MTMDET), under the Government assistance program for the public transport of people.

 

Work began in January 2017 and will be completed in winter 2019. 

Projet objectives

  • Enable intermodal access for people with reduced mobility between Terminus Centre-ville, Bonaventure metro station and De la Gauchetière Street.

  • Pursue projects that will ensure universal access to our facilities in compliance with applicable regulations and customer expectations.

Site plan

Plan Terminus Centre-ville

Project description

Three (3) elevators will be built to allow users with reduced mobility to circulate between the metro station, Terminus Centre-ville and De la Gauchetière Street:

  • An elevator will link the ground level of 1000 De la Gauchetière to the terminal’s north platform;

  • A second will link the terminal’s centre and south platforms to the ground level of 1000 De la Gauchetière;

  • A third will link the mezzanine level of the Bonaventure metro station to the terminal’s centre and south platforms.

Work schedule

  • Construction: January 2017 – Winter 2019

  • Commissioning: Winter 2019

Partners

  • MTMDET
  • Ivanhoé Cambridge (owner of 1000 De la Gauchetière)
  • STM
  • RTL